title: How a Machinery Move Works, Step by Step | ILS
url: https://machinerymovingnv.com/guides/how-machinery-moving-works/
business: Industrial Logistics Services, Inc. (ILS)
what: machinery moving, rigging, millwright services, installation and alignment, plant relocation, machinery transport, crating, storage
phone: (775) 882-3319
fax: (775) 882-2693 (fax only)
email: johns@ilsmachinerymoving.com
address: 3868 Goni Rd, Carson City, NV 89706
hours: Mon-Fri 7:00 am - 4:00 pm, Sat-Sun closed
licenses: Nevada contractor licenses 0046276, 0083124, 0083125; USDOT 642556, MC-531191
estimates: free
---

- [Home](https://machinerymovingnv.com/)
- [Guides](https://machinerymovingnv.com/guides/)
- How a machinery move works, step by step

# How a machinery move works, step by step

A machinery move runs in seven stages: estimate, site survey, planning, disconnect and lockout, rigging and loading, transport, and setting and leveling at the new location. The owner handles the energy sources and the facility, and the mover handles the lift, the haul and the placement.

Key points

- Seven stages: estimate, survey, plan, disconnect, rig and load, transport, set and level
- Weight, size and the route decide the method more than the miles do
- The plant locks out and disconnects utilities; the mover rigs and hauls
- Setting and leveling at the new spot finish the job, not the delivery
- Estimates are free and start from a few facts about the machine

Whether the job is one CNC machine or a whole production floor, the order of work is the same. Knowing the order lets you see where your own staff fit in and what to have ready. ILS is a licensed Nevada contractor in machinery installation (C-33) and rigging (C-14I), and its crews follow this sequence on jobs from a single machine up to equipment weighing up to 300 tons.

## The seven stages

Each stage depends on the one before it, which is why skipping the survey or the plan is the usual cause of delays and surprises.

- Estimate: you give the machine type, size, weight, pickup and set-down addresses and photos. The office reviews them and returns a free estimate.
- Site survey: the crew or estimator looks at doors, aisles, floors, overhead clearance, dock height and the path the machine will travel.
- Planning: weight, center of gravity and lift points are confirmed, the method is chosen (forklift with rigging boom, gantry, skates, or a mix), and the trailer is matched to the load.
- Disconnect and lockout: the plant de-energizes and locks out the machine, and electricians, plumbers or millwrights disconnect power, air, water and controls.
- Rigging and loading: the machine is lifted or skidded out, secured, and loaded on the truck or trailer.
- Transport: the load travels on ILS trucks for local work, or through a network of trucking companies on long-distance moves, within legal size and weight limits.
- Set, level and reconnect: the machine is placed on its pad or foundation, leveled and aligned, and handed back for reconnection and start-up.

## Who does what

A clear split of duties keeps the day safe. The owner knows the machine and the plant, so the owner supplies the weight and manual, decides who disconnects utilities, and keeps production staff out of the work zone. The mover brings the lifting equipment, the rigging gear and the trucks. If something does not match the plan, such as a bolt nobody knew about, work stops and the plan is changed before anything is lifted. For the disconnect step, [lockout/tagout before a machinery move](https://machinerymovingnv.com/guides/lockout-tagout-before-a-move/) explains the rule in detail.

## How the method is chosen

The machine and the building pick the method. A machine on a pallet or with fork pockets may go on a forklift with a rigging boom. A tall or top-heavy unit may need a gantry, and a machine on a tight route may go on skates and rollers. ILS publishes forklifts from 3,000 lbs. to 100,000 lbs. with rigging booms, a 2-ton portable aluminum gantry and a 300-ton hydraulic gantry system. The right one for your machine is a planning decision, not a catalog choice. See [lift planning basics](https://machinerymovingnv.com/guides/lift-planning-basics/) for how that decision is made.

## Transport and the road

Once the machine is on a trailer, Nevada's size rules apply. A load over 14 feet high, 70 feet long as a combination, or 102 inches wide needs a permit from the Nevada Department of Transportation (NRS 484D.605, 484D.615 and 484D.725). Equipment trailers to 50 tons carry most machines, and the trailer deck height matters as much as the machine. Details are in [Nevada oversize load permits explained](https://machinerymovingnv.com/guides/nevada-oversize-load-permits/).

## Setting, leveling and reconnecting

Delivery to a building is not the end. The machine goes onto its pad or foundation, is leveled, and is aligned if the machine needs it. ILS uses optical levels and theodolites (1 arc second), high accuracy laser levels, and spirit levels (accurate to .0005" in 12"). After that the machine is reconnected and run; who reconnects it is agreed in the estimate. Bolting a machine permanently to a structure is contractor work in Nevada under NAC 624, which is why the installer's license class matters. Read [Nevada contractor license classes](https://machinerymovingnv.com/guides/nevada-contractor-license-classes/) for what each class covers.

## What to have ready before you call

You can speed up an estimate by collecting a few things. The machine's nameplate or manual usually gives weight and dimensions. Photos of the machine, the doors it must pass through and the path to the dock help the estimator more than a long description does. Use the [machine measuring worksheet](https://machinerymovingnv.com/tools/machine-measure-worksheet/) and then ask for a free estimate.

### Sources (3)

- U.S. Occupational Safety and Health Administration : [osha.gov/laws-regs/regulations/standardnumber/1910/1910.147](https://www.osha.gov/laws-regs/regulations/standardnumber/1910/1910.147) (checked November 2026)
- Nevada Legislature : [leg.state.nv.us/nrs/nrs-484d.html](https://www.leg.state.nv.us/nrs/nrs-484d.html) (checked November 2026)
- Nevada State Contractors Board : [app.nvcontractorsboard.com/Clients/NVSCB/Public/ContractorLicenseSearch/ContractorLicenseS](https://app.nvcontractorsboard.com/Clients/NVSCB/Public/ContractorLicenseSearch/ContractorLicenseSearch.aspx) (checked November 2026)

### Send the machine details

Type, size, weight, where it is and where it is going. Photos help. Estimates are free.

[Start the estimate](#estimate)

### Licensed in Nevada

Nevada State Contractors Board licenses 0046276 (C-33 Installing Industrial Machinery), 0083124 (A-14, A-20) and 0083125 (C-14I Rigging and Cranes, C-14J Conveyance of Goods). USDOT 642556, MC-531191.

[What the classes cover](https://machinerymovingnv.com/guides/nevada-contractor-license-classes/)

### Keep reading

- [Machinery moving](https://machinerymovingnv.com/services/machinery-moving/)
- [How to measure a machine for a moving estimate](https://machinerymovingnv.com/guides/how-to-measure-a-machine/)
- [How to prepare a machine before the riggers arrive](https://machinerymovingnv.com/guides/prepare-a-machine-for-moving/)
- [Lift planning basics for plant managers](https://machinerymovingnv.com/guides/lift-planning-basics/)
- [Free estimate](https://machinerymovingnv.com/free-estimate/)

## Questions we hear

[All questions](https://machinerymovingnv.com/faq/)

### How long does a machinery move take?

It depends on the machine, the route and how much disconnecting and leveling is involved, so the duration is set in the estimate. The estimate and site survey establish the plan, and the schedule follows from it.

### Do I need to be on site?

Someone who knows the machine and the plant should be reachable, because the crew needs answers about utilities, lift points and where the machine goes. The plant also controls lockout and who enters the work zone.

### Can ILS move a single machine?

Yes. Single machines are welcome, and so are whole plants. ILS has the capacity of moving and relocating equipment weighing up to 300 tons, and the estimate is free.