Planning a plant relocation
Plan a plant relocation backward from the day production must restart, and sequence machines so the ones you need first are installed first. Most of the work happens before any machine moves: surveying the equipment, designing the new layout, preparing foundations and utilities, and agreeing who does what.
- Nevada Contractors License 46276
- USDOT 642556 · our own trucks
- 4.6 on Google (15 reviews)
Key points
- Build the equipment list first: every machine, its weight, size and utility needs
- Design the new floor plan around machine sequence, not just available space
- Foundations, power and air need to be ready before the machine arrives
- Lockout and disconnect are the plant's responsibility, coordinated with the movers
- Plan the restart: leveling, alignment, test runs and operator sign-off
Moving a plant is a project with a start-up at the end of it, not a series of truck trips. This guide lays out the phases most relocations follow. It describes generally accepted practice and is not a promise of a particular schedule; your own timeline depends on the machines, the building and the permits involved.
Phase 1: survey the equipment
Start with a walk-through of the existing plant with a spreadsheet. For each machine record the maker, type, nameplate weight, overall dimensions, power and air requirements, any foundation or anchor bolts, and whether it can be moved whole or needs to be taken apart. Photograph each machine and the path it will leave by.
This list becomes the basis for every estimate that follows. Guides on measuring a machine and preparing it for moving cover the detail.
Phase 2: design the destination
Lay out the new space with the machines in production order. Check door and ceiling clearances against the biggest items, floor capacity against the heaviest, and where utilities enter. Machines that need pits, isolated pads or special flooring should be identified now, because concrete takes time to cure and engineering takes time to produce. See floor loads, anchors and foundations.
Phase 3: choose the waves of the move
Few plants shut everything at once. A common approach is to move in waves, with support equipment and compressors set first, then the lines in order of production importance. Each wave needs its own disconnect, rigging, transport, set and reconnect window.
Decide which machines may go on a truck whole and which require permits. A load over 14 feet high, over 70 feet long or wider than 102 inches needs an NDOT over-dimensional permit in Nevada, and our oversize load checker shows those limits.
A working checklist
- Confirm the restart date and work backward from it.
- Complete the equipment survey and weight list.
- Get written estimates for rigging, transport and installation from the same scope sheet.
- Finalize the floor plan and any foundation or utility drawings.
- Pour and cure foundations; run power, air and water to the new locations.
- Schedule disconnects and lockout with your maintenance team.
- Tag every machine and every disconnected line so reconnection matches.
- Move in waves; set, level and anchor each machine as it arrives.
- Reconnect utilities, test and align, then release to production.
Who does what
Relocations go wrong at the handoffs. Put a name next to each task before the first machine moves.
| Task | Usually handled by |
|---|---|
| Lockout, drain and disconnect | Plant maintenance or its electrical and plumbing contractors |
| Rigging, loading and hauling | Machinery mover and rigger |
| Foundations and anchors | Engineer and concrete contractor, with the mover for layout |
| Leveling and alignment | Millwright or installer, with machine maker's specs |
| Utility reconnection and test | Plant maintenance or licensed trades |
ILS describes its own relocation work as handling a project from start to finish, including engineering services, foundations and specialized transportation. See plant and factory relocation for the scope.
The restart
The move is not finished when the machine is on its pad. Level and align it, tighten anchors to the maker's specification, reconnect and test. Keep operators involved: they notice vibration, noise or behavior that a technician with an instrument may miss. Keep the old building's records until the new floor has run a full production cycle.
Sources (3)
- Nevada Legislature: leg.state.nv.us/nrs/nrs-484d.html (checked November 2026)
- U.S. Occupational Safety and Health Administration: osha.gov/laws-regs/regulations/standardnumber/1910/1910.147 (checked November 2026)
- U.S. Occupational Safety and Health Administration: osha.gov/machine-guarding (checked November 2026)
Send the machine details
Type, size, weight, where it is and where it is going. Photos help. Estimates are free.
Start the estimateLicensed in Nevada
Nevada State Contractors Board licenses 0046276 (C-33 Installing Industrial Machinery), 0083124 (A-14, A-20) and 0083125 (C-14I Rigging and Cranes, C-14J Conveyance of Goods). USDOT 642556, MC-531191.
What the classes coverHow far ahead should I start planning?
Start as soon as the move is likely. Surveys, drawings, permits and concrete cure time all take calendar time that cannot be compressed on move day.
Can the mover handle foundations?
ILS describes engineering services and foundations as part of a full relocation project. Confirm in writing which parts are in the scope and which stay with your engineer.
Do I need to shut the whole plant down?
Usually not. Moving in waves lets part of the plant keep running, though each wave still needs its own isolation and restart.
Free estimates
Tell us what needs moving.
Free estimates on every job, big or small. Call the office or send the machine details and we will call you back.
(775) 882-3319Monday to Friday, 7:00 am to 4:00 pm. Fax (775) 882-2693.
- Nevada Contractors License 46276
- USDOT 642556 · our own trucks
- Carson City since 1999
- 4.6 on Google (15 reviews)